Spotlight on Building Consent Delays

The coalition Government is taking steps to reduce delays and speed up the building consent system by requiring councils to submit data for building consent and code compliance certificates every quarter, Building and Construction Minister Chris Penk says.

“Applications for building consents and code compliance certificates must be completed within 20 working days, however feedback from the sector is that they often take a lot longer causing frustrating and costly delays for builders.   

“Delays in the building consent system increase the cost of building and make it harder for the sector to deliver more affordable homes for Kiwi families.

“Unbelievably, there is currently no consistent nationwide data on building consent timeframes and while MBIE has the power to collect it regularly the previous Labour Government never bothered to ask for it. 

“This will change and starting in April, Building Consent Authorities will be required to submit timeframes for building consent and code compliance certificate applications with this data being published on MBIE’s website every quarter. 

“This added scrutiny will provide greater certainty for the sector, encourage best practice and drive innovation that will help reduce delays and let Kiwi builders get on with the job.  

“Collecting this data is also an important early step that will help inform future changes in the Government’s ambitious plan to streamline the building consent system and make it easier to build.”

Notes for editors: 

Processing times for building consent and code compliance certificate applications for quarter one 2024 will be published in the week of the 29th April.